NEW QUESTION 64
In the planning of a new major manufacturing program, the greatest quality effort should be put logically in
- A. Nonconformance to specifications.
- B. Prevention of occurrence of substandard quality.
- C. Nondestructive testing equipment.
- D. Inspection of product.
Answer: B
NEW QUESTION 65
Maintainability is
- A. Performing adequate maintenance on a system.
- B. Maintaining a machine in satisfactory working condition.
- C. The probability of a system being restored to functional operation within a given period of time.
- D. Probability of survival of a system for a given period of time.
Answer: C
NEW QUESTION 66
A comprehensive corrective action program is initiated at a large company. Input for CARs are received from customers, internal and external audits, material review reports and other sources. Which two of the following groups would usually administer and control the CAR process?
. Management review team.
. Quality department.
. Corrective Action Board.
. Material Review Board.
- A. IIIandIVonly
- B. I andIIonly
- C. I andIIIonly
- D. IIandIIIonly
Answer: C
NEW QUESTION 67
The primary advantage of the Latin square design, compared to the factorial design, is that
- A. It does not require homogeneity of variance.
- B. It allows higher significance levels.
- C. In most circumstances, it requires less data.
- D. It eliminates the need for interaction analysis.
Answer: C
NEW QUESTION 68
A cause and effect diagram is also called which of the following?
- A. Fishbone diagram.
- B. Histogram.
- C. Pareto diagram.
- D. Boxplot.
Answer: A
NEW QUESTION 69
What percentage of the area under the standard normal curve is included within (+/-) 1.5 standard deviations from 0?
- A. 0.9332
- B. 0.6680
- C. 0.8664
- D. 0.7500
Answer: C
NEW QUESTION 70
The AQL for a given sampling plan is 1% this means that
- A. All lots are 1% defective or better.
- B. All accepted lots are 1% defective or better.
- C. The average quality level of the plan is 1%.
- D. The producer takes a small risk of rejecting product which is 1% defective or better.
Answer: D
NEW QUESTION 71
The power of efficiency in designed experiments lies in the
- A. The sequential and cyclical procedure of conjecture to design to analysis and back to conjecture.
- B. Random order of performance.
- C. Hidden replication.
- D. The large number of possible combinations of factors.
Answer: C
NEW QUESTION 72
Typically Pareto diagrams are used for which of the following reasons?
. To display the significant few categories. . To compliment attribute data charting. . To eliminate insignificant categories.
. To focus attention in priority order.
- A. II,IIIandIVonly
- B. I andIIIonly
- C. I,II,IIIandIV
- D. I,IIandIIIonly
Answer: C
NEW QUESTION 73
The Dodge-Romig tables are designed to minimize which of the following parameters?
- A. AQL
- B. ATI
- C. AOQ
- D. AOQL
Answer: B
NEW QUESTION 74
In order to implement a continuous improvement strategy, a company may institute a steering committee or improvement council. Which of the following would generally NOT be a task performed by this council?
- A. The development of quality education and communication modules for the organization.
- B. The definition of certain quality objectives for sections of the company.
- C. The combined development and implementation of the company improvement strategy.
- D. The development of a quality vision for the company.
Answer: D
NEW QUESTION 75
Which of the following control charts are more efficient than an X-bar chart at detecting small shifts in the mean?
I. CUSUM.
II. EWQR.
III. EWMA.
- A. II only
- B. III only
- C. I and III only
- D. I only
Answer: C
NEW QUESTION 76
Analysis of data on all product returns is important because
. Failure rates change with length of product usage.
. Changes in design and in customer use are often well reflected.
. Immediate feedback and analysis of product performance becomes available.
- A. I,IIandIII
- B. I only
- C. I andIIIonly
- D. IIandIIIonly
Answer: A
NEW QUESTION 77
Which of the following distributions models events that have 2 possibilities on each trial?
- A. Normal.
- B. gamma.
- C. Poisson.
- D. Binomial
Answer: D
NEW QUESTION 78
The Malcolm Baldrige award is open for competition among which of the following?
I. Large manufacturing businesses.
II. Large and small manufacturing businesses.
III. Service organizations.
IV. Large service companies.
- A. II and IV only
- B. I and III only
- C. I only
- D. II and III only
Answer: D
NEW QUESTION 79
For TQM success, what structure sequence should be followed?
I. Develop a quality policy.
II. Establish a quality council.
III. Establish strategic quality goals.
IV. Train for internal audits.
- A. III, II, I, IV
- B. II, I, III, IV
- C. I, II, III, IV
- D. II, III, I, IV
Answer: B
NEW QUESTION 80
The existence of a quality control manual at your key supplier means
- A. That a quality system has been implemented.
- B. That the firm is a certified supplier.
- C. That a quality system has been developed.
- D. That the firm is quality conscious.
Answer: C
NEW QUESTION 81
In the planning of a new major manufacturing program, the greatest quality effort should be put logically in
- A. Nonconformance to specifications.
- B. Prevention of occurrence of substandard quality.
- C. Nondestructive testing equipment.
- D. Inspection of product.
Answer: B
NEW QUESTION 82
Which of the following control charts are more efficient than an X-bar chart at detecting small shifts in the mean?
. CUSUM.
. EWQR.
. EWMA.
- A. IIIonly
- B. I only
- C. I andIIIonly
- D. IIonly
Answer: C
NEW QUESTION 83
......
Authentic Best resources for CQE Online Practice Exam: https://www.braindumpsvce.com/CQE_exam-dumps-torrent.html
Updates Up to 365 days On Developing CQE Braindumps: https://drive.google.com/open?id=1vE9z-Qz_0AphzyLYry39Mc7gkKwbO3Ia